Punch list · Guide
Punch list vs snag list: same job, two names
A punch list and a snag list are the same thing: the defects and unfinished work found before a building is accepted. The US says punch list; the UK, Ireland and Australia say snag list. The contract words around the list differ more than the list itself.
SheetPL-07
TitlePunch list vs snag list
- For
- Builders and contractors
- Sheet type
- Guide
- Words
- US English: punch item, closeout, retainage
- Revised
- 20 Oct 2026
The same job in two vocabularies
Read across a row: the US word, the UK and Irish word, and what both mean on site.
| US | UK and Ireland | What it means |
|---|---|---|
| punch list | snag list | The list of defects and unfinished work before acceptance |
| punch item | snag | One thing on the list |
| punch walk | snagging, snagging inspection | Walking the building to make the list |
| back-punch | re-inspection | Re-walking open items to confirm each fix |
| substantial completion | practical completion | The building can be used, with only minor items left; the formal list is written here |
| closeout | handover | Passing the finished building and its documents to the owner |
| retainage | retention | Money held back from each payment until the work is accepted |
| warranty period | defects liability period, rectification period | Time after completion when the builder fixes defects that appear |
| general contractor (GC) | main contractor | The firm holding the building contract |
| superintendent | site manager | The builder’s person running the site day to day |
| owner’s rep, architect | employer’s agent, contract administrator, clerk of works | The people who walk the list for the client |
| caulk | mastic, sealant | The bead at tubs, counters and trim |
| baseboard | skirting | The trim at the bottom of a wall |
| drywall | plasterboard | Wall and ceiling board |
| countertop | worktop | The kitchen work surface |
| faucet, outlet, elevator | tap, socket, lift | Same fittings, different names |
| first floor | ground floor | The floor at street level, so a US second floor is a UK first floor |
What actually differs in practice
Who walks the list. On US commercial and multifamily work, the architect or owner’s rep writes the punch list at substantial completion, after the GC’s superintendent has run a pre-punch. On UK new-build housing, the buyer often pays an independent snagger to walk the home after completion, and the housebuilder’s customer care team works through that list under the new-home warranty. The list is the same; the person holding the pen is not.
When the money moves. In the US, the retainage held back from every pay application comes back once the punch list is closed and the closeout documents are in. In the UK, retention works the same way, but on many standard-form contracts part of it comes back at practical completion and the rest at the end of the defects liability period.
How the report reads. A US report says color and October 20, 2026. A UK report says colour and 20 October 2026, and calls the second floor the first. If your firm works on both sides of the Atlantic, the report should match the client, not the office.
Running either list in Easy Site Audit
The walk and the evidence are identical. A few settings make each report read right for its client.
Rename the terms
In Settings → Customization, change Issue to Punch item or Snag, Assigned To to Trade, and Report to whatever your client calls the walk. The words apply across the app and every PDF, so switch them before you start a job in the other market.
Pick the checklist for the market
US punch lists such as the new home punch list, or UK snag lists such as the new-build snagging list. Both sit in the Construction library’s handover and closeout stage.
Set the date format
Choose from 24 date formats so the report prints dates the way the client writes them.
Send the same evidence
Photos, markup, trades and comments print the same way in either market. The report is white-label, so only your logo, signature and name appear on it.
Words to check before a report crosses the Atlantic
- Item name: punch item or snag, set in Settings → Customization.
- Assignee label: Trade, Sub or Contractor.
- Dates: month first for US clients, day first for UK and Irish clients.
- Floor names: write the floor the way the client numbers it.
- Finishes in item titles: caulk or mastic, baseboard or skirting, drywall or plasterboard.
- Contract terms in comments: substantial or practical completion, retainage or retention.
- Measure tool units: inches and feet, or millimeters and meters.
One library, both vocabularies
US punch lists and UK snag lists from the same handover and closeout stage.
Keep reading on punch lists
For the US side in depth, read what is a punch list and how to run a punch walk, or see how closeout runs on punch list software from Easy Site Audit.
Questions people ask
Is a snag list the same as a punch list?
Yes. Both list the defects and unfinished work to correct before a building is accepted. Punch list is the US and Canadian term; snag list is used in the UK, Ireland, Australia, New Zealand and the Middle East. The difference is vocabulary, not the inspection.
What is snagging called in the US?
A punch walk, or walking the punch list. The re-check of open items is often called a back-punch, and the finished list is attached to the certificate of substantial completion rather than to a practical completion certificate.
Is practical completion the same as substantial completion?
They play the same role. Both mark the point where the building can be used for its purpose with only minor items left, and both are when the formal list is written. The exact definition depends on the contract, so check the one you signed.
Can one Easy Site Audit account produce both punch lists and snag lists?
Yes. Rename Issue to Punch item or Snag in Settings → Customization, pick a US or UK checklist from the Construction library, and choose the date format. The wording applies across the app, so change it before you switch markets.