Snagging is the inspection that finds what is unfinished, damaged or wrong in a new or refurbished building, so it is put right before handover or during the defects period. Each defect is a snag, and the snag list is the record of who fixes what.
SheetS-02
TitleWhat is snagging?
- For
- Builders and contractors
- Sheet type
- Guide
- Words
- UK English: snag, handover, retention
- Revised
- 20 Oct 2026
Where the word comes from, and who uses it
A snag is a small thing that catches: a defect that stops the job being finished properly. The word is used across the UK and Ireland, Australia, New Zealand and the Middle East. In the US the same list is called a punch list, and the walk is a punch walk.
Snagging covers two different jobs. On a contract, the main contractor’s site manager snags before calling practical completion, and the client’s side (an employer’s agent, a clerk of works or the architect) snags again before accepting it. On new homes sold privately, the buyer or a professional snagger they hire walks the house after completion and sends a list to the housebuilder’s customer care team.
The defects are the same in both: mostly finishes. Paint, mastic, skirting, doors, windows, the kitchen and the bathroom account for most of a typical residential snag list. Structural problems are rare on a snag list; when they turn up, they are a warranty claim, not a snag.
Who snags, and when
The same building can be snagged four times. Each walk has a different owner and a different purpose.
| Walk | Who does it | What it is for |
|---|---|---|
| Pre-handover snag | The site manager or a finishing foreman | Find and fix everything before the client or buyer sees it, so practical completion isn’t refused |
| Practical completion inspection | Employer’s agent, clerk of works or contract administrator | Agree that the works are complete apart from minor defects, and agree the list of those defects |
| Buyer’s snag | The homeowner or a professional snagger they hire | Record defects after completion so the housebuilder fixes them under the warranty |
| End of defects period | The client’s side and the contractor together | Check the making good is done, so the last of the retention can be released |
How to snag a property, step by step
The method a careful site manager or professional snagger follows. It works on a two-bed flat or a forty-plot phase.
Get the paperwork before the torch
Have the drawings, the finishes spec and the kitchen layout with you. A snag is anything that doesn’t match what was sold or specified, so you can only snag the wrong worktop if you know which worktop was ordered.
Bring the kit
A strong torch held flat to the wall shows every roller mark and patch. Add a spirit level, a tape, a socket tester, low-tack tape to mark defects on site, and a stepladder for the loft hatch and the top of the wardrobes.
Walk in a fixed order
Start at the top and work down, and go round each room the same way: ceiling, walls, windows, doors, floor, then fittings and services. A fixed order is what stops you missing the en-suite on plot 9 because you got distracted by the boiler on plot 8.
One defect, one snag
Record each defect on its own with a photo. “Bed 2: paint” is not a snag. “Bed 2, window wall: roller marks and a patch to the right of the reveal” is. Two defects in one line means one of them gets forgotten.
Write it for the trade, not for yourself
Say the room, the element and the fix: “Kitchen: mastic missing behind the sink, 300 mm, re-seal”. Put the trade against every snag, so the list can be split up and nobody argues about whose it is.
Issue the list, then re-inspect it
Send each trade its snags with the photos, agree when they will be back, and walk the list again when they say it is done. Add the after photo, mark the snag complete, and only then is it off the list.
Sign it off
The finished list, with the defects, the fixes and the sign-off, is the record behind practical completion, the handover pack and the retention. Keep it with the plot.
What counts as a snag
If it is unfinished, damaged, missing, not working or not as specified, it is a snag.
- Poor finish: roller marks, paint on glass and sockets, uneven cutting-in, gappy mastic, open mitres on skirting and architrave.
- Damage: chipped tiles, scratched glazing, dented doors, marked worktops, torn carpet at the threshold.
- Missing items: door stops, plinths, trickle vent covers, bath panels, keys, appliance manuals.
- Things that don’t work: a door that won’t latch, a window that won’t lock, an extractor fan that doesn’t run, a radiator that stays cold.
- Not as specified: the wrong tiles, a different tap, sockets in the wrong place, a fence that isn’t on the plot boundary.
- Safety snags, recorded as High priority: a fire door that doesn’t close onto its latch, a missing smoke alarm, a loose handrail.
What usually isn’t a snag
Fine shrinkage cracks that appear as new plaster and timber dry out are normal in the first months of a new home. Housebuilders usually deal with them once, later in the defects period, rather than on the handover list. Snag them if they are wide, if they keep growing, or if a door has started to bind.
Design choices you don’t like aren’t snags unless they differ from what was sold. A snag list full of opinions gets the real defects ignored along with them.
How snagging ties to practical completion and retention
On a contract job, practical completion is the point the client takes the building back. The contract administrator certifies it when the works are finished apart from minor defects, and the snag list is the evidence both sides use to agree what “minor” covers. On many standard-form contracts, part of the retention is released at practical completion and the rest at the end of the defects period, once the making good is checked.
That makes the snag list a financial document as much as a quality one. A list that shows each defect, who fixed it and a photo of the repair shortens the end-of-defects inspection and the argument about money that follows it.
Snagging on an iPhone or iPad
A paper list or a spreadsheet records the defect and loses the fix. In the Easy Site Audit app you photograph each snag (up to 5 photos per snag), mark it up with an arrow or a measure line, write the trade in “Assigned To”, and add the after photo to the same snag on the re-inspection. The report is an A4 PDF with your logo and signature, ready to send before you leave site, and the app works with no signal.
Start from a ready-made checklist such as the new-build snagging list or the snagging checklist, free on every plan. For how a whole handover runs on Easy Site Audit, see snagging software.
Questions people ask
Is snagging the same as a building survey?
No. A survey assesses the condition and structure of a building, usually before you buy it. Snagging checks a new or refurbished building for defects in the finished work, such as paint, mastic, doors and fittings, so the builder puts them right.
When should a new-build buyer snag the house?
Ideally before completion, if the housebuilder allows a pre-completion inspection, and again soon after moving in. Snag before the furniture goes in: defects behind wardrobes and sofas are hard to see and easy to dispute later.
Who pays to fix snags?
The builder or contractor responsible for the work. On a contract that is set by the defects clauses; on a new home sold privately it is covered by the housebuilder’s customer care process and the warranty. The snag list with photos is what you send them.
What should a snag list include?
Each snag on its own line: the room, the element, the defect and the trade that fixes it, with a photo. When it is fixed, add the after photo and a comment saying when it was checked, and the list becomes the record behind handover and the retention.