Snagging · Report
Snagging report template and example
A snagging report is the document that leaves site with the keys: every snag with its photos, room and trade, the checks you made, and your signature on the cover. In the Easy Site Audit app it builds from the walk itself, as a branded A4 PDF.
A report the trades can fix from and the client can sign against, sent before you leave site.
SheetS-06
TitleSnagging report
- For
- Builders and contractors
- Sheet type
- Template
- Words
- UK English: snag, handover, retention
- Revised
- 20 Oct 2026
What a snagging report is for
Three people read a snagging report, and each wants something different. The trade wants to find their snags fast and see exactly what is wrong. The client, the employer’s agent or the buyer wants to see that the property was checked properly and what is still open. And six months later, when someone asks whether the bathroom sealant was ever redone, you want a dated photo you can point to.
A good report serves all three: one entry per snag with a clear title and a photo, the trade against each one, and a signed cover that says who walked it and when.
What the report covers
Every snagging report from the Easy Site Audit app has the same parts, in this order.
Cover
- Your company logo, set once and changeable per report.
- The project title, the report name and the date, in any of 24 date formats.
- The number of snags found, in your own words if you rename Issue to Snag and Identified to Found.
- Your on-screen signature, with the inspector’s name and company.
- A cover photo of the plot, in the Corporate and Photographic themes.
The snags
- One entry per snag, with the title you gave it: room first, then the defect.
- Its photos, up to 5, with any arrows, circles, text or measure lines you drew.
- The colour tag and the trade from “Assigned To”, so each trade can find their own snags.
- Comments under the snag: what was agreed, and when the fix was checked.
The checklist
- How many checklist questions were answered, and each section’s progress.
- Each answer with its score, your note, and any photos you attached.
- The comments and action plan on answers that needed one: what needs fixing, who, by when.
Layout options
- Photo size and text size, each from four settings.
- Page numbers, and Timestamp Report Photos to print the date on every photo.
- Leave out the photos or the checklist when a reader doesn’t need them.
- Several reports from the same plot merged into one PDF.
An example, page by page
A fictional report for Plot 14 at Ashby Meadows, a three-bed semi, after the pre-handover walk and two re-inspections.
- Cover. The builder’s logo, “Plot 14, Ashby Meadows: pre-handover snagging”, the date, “Found 38 snags”, and the site manager’s signature, name and company over a photo of the front elevation.
- Pages 2 to 9: the snags, in walking order. “Bed 2, door: skirting mitre split, left side” with two photos and an arrow on the joint, tagged Red for the joiner. “Kitchen: mastic missing behind sink, 300 mm” with a measure line, tagged Yellow for the plumber.
- Each fixed snag carries the after photo beside the before, and a comment: “Re-sealed. Checked 3 November, OK.”
- The re-inspections are merged into the same PDF after the original walk, so the client gets one document for the plot.
- The last pages: the checklist. The new-build snagging checklist with its sections and progress, notes against the answers that needed one, and the action plan for the back door.
The 8 report themes
Every theme is white-label on every plan: no watermark and no “made with” footer. Basic is the default.
| Theme | What the cover looks like |
|---|---|
| Corporate | Your cover photo under a dark overlay, with the logo and title centred |
| Photographic | A full-page cover photo with the title over it, magazine style |
| Modern Bold | A big title low on the page with a red underline; red bar on each snag |
| Minimal | Left-aligned and spacious, with a dark blue title |
| Bright Blue | A solid blue panel with white text |
| Financial | A green panel under the logo, with a green rule above each snag |
| Legacy | Classic and fully centred |
| Basic | A plain document with the logo top left; the default |
Who sends a snagging report, and to whom
Site manager to trades
The pre-handover snag walk, sent to the trades the same day so they can start making good.
Site manager to client
The signed report at practical completion, for the employer’s agent or the sales office.
Snagger to buyer and builder
The professional snagger’s report for the homeowner, sent on to the housebuilder’s customer care team.
End of the defects period
The making-good check, with every fix photographed, behind the release of the last retention.
Use this checklist free in the app
Checklists are free to browse, add and fill in on every plan. Start the report from one of the snagging checklists below.
Add a snagging checklist to the plot
Download the Easy Site Audit app, create a project for the plot, and add a checklist from the Construction library’s handover and closeout stage.
Walk it and record the snags
Answer the checks and add each defect as its own snag with photos, markup and the trade.
Set up the report once
Add your logo and signature, pick a theme, and choose photo size, text size and the timestamp option. Your logo is set once for every project.
Generate and send
Name the document, then email it, send it with the iPhone and iPad share options, or print it.
More on reports and snagging
For the full set of report themes across every kind of inspection, see report themes for every inspection. For how the report fits into a handover, from the first walk to sign-off, see snagging software.
Questions people ask
Can I send the snagging report as Word or Excel?
No. Reports are A4 PDFs, which you can email, share from your iPhone or iPad, or print. A PDF keeps the photos, markup and signature together, and the trade or client can open it without an account.
Does the report carry Easy Site Audit branding?
No. Reports are white-label on every plan, with no watermark and no “made with” footer. Only your logo, signature, company and inspector name appear.
Can I put the snag walk and the re-inspection in one report?
Yes. A project can hold several reports, and you can merge them into one PDF, so the original snag walk and each re-inspection go to the client as a single document.
Can the report say snags instead of issues?
Yes. Under Settings → Customization, rename Issue to Snag, Identified to Found and Assigned To to Trade. The app and every report then use your words.